Gypsum factory II
Gypsum factory renovation Phase II is a logical follow-up to the Phase I. The aim of the project was to complete the architectural ensemble of the former Gypsum factory. The project proposes to renovate the existing valuable buildings and to introduce within the scenery of the riverside and within the context of the factory ensemble significant new architectural volume. Gypsum factory ensemble manifests rehabilitation and humanisation of industrial brick architecture. The loft principle is encoded both within the common compo…
read moreGypsum factory II
Gypsum factory renovation Phase II is a logical follow-up to the Phase I. The aim of the project was to complete the architectural ensemble of the former Gypsum factory. The project proposes to renovate the existing valuable buildings and to introduce within the scenery of the riverside and within the context of the factory ensemble significant new architectural volume. Gypsum factory ensemble manifests rehabilitation and humanisation of industrial brick architecture. The loft principle is encoded both within the common composition of the ensemble and within the structure of separate residential units. It can be recognised as a search for a new generation versions of living spaces.
The ensemble consists of four buildings: the Old House, four Villas, Ogļu street House and the Red House. The buildings are located around two inner courtyards which are designed as green gardens. Colours of the ensemble are pale yellow, red and black. Variations and combinations of the colour palette are used throughout the design of the common image. The new buildings are made of bricks which are specifically produced in Switzerland for this project. The same bricks are also used in interiors of the apartments. All apartments are planned to be sold or rented with as design apartments decorative finish.
Conversion of industrial ensemble into residential complex with 62 apartments, underground parking space and two courtyards
Riga, Ķīpsala, Balasta dambis 72
Architects: Zaiga Gaile, Liene Griezīte, Iveta Cibule, David Moed, Ingmārs Atavs, Agnese Sirmā, Zane Dzintara, Ineta Solzemniece- Saleniece
Participated: Andra Šmite, Māris Līdaka, Liene Zemīte, Gints Lūsis-Grīnbergs
Client: “Domuss” Ltd.
Project: 2004 - 2013
Construction: 2006 - 2013
Total space of the site: 5022 sq.m.
Construction site: 3256 sq.m.
Number of apartments: 62
Total space of the apartments: 7807sq.m.
Basement: 4300 sq.m.
Underground parking for 80 cars